Procurement
Process
RFQs
are distributed via closed invitation to registered suppliers.
Contracting
specifications:
·
General liability insurance is usually from $5 million to $10
million. Insurance can be required of up to $25 million on a very
high risk project.
·
UP
requires that the railroad be named as an additional insurer
·
Bonds may be required (e.g. in the case of a new contractor)
·
Health and safety plan is required
·
Minimum warranty of one year is required
·
Dispute resolution will go to arbitration
·
UP
requires that a project manager be committed for the duration of a
job, which is important for quality of work product.
If you are
interested in becoming a service provider, complete the Bidder’s
List Registration form under “Contract Services”at:
www.uprr.com/suppliers/index.shtml |