Project P4 Public Meeting - December 2011
Public meetings for the Grand Crossing Rail Project (P4) are 4:00-7:30 p.m. on December 12, 2011, Grand Crossing Park Field House, 7655 S. Ingleside Avenue and December 13, 2011, Sherman Park Field House, 5701 S. Shields Avenue.
The meeting materials are available at www.grandcrossingrail.com.
Projects P2, P3, EW2, GS19 Public Meetings - October 27, 2011
The next Public Meeting for CREATE 75th Street Corridor Improvement Project will be October 27, 2011. For more information, please visit: www.75thcip.org.
Project B4B5 Public Meeting Notice - March 22, 2009
Project B4B5, located along the Indiana Harbor Belt rail line, is just less than 8 miles long from North Avenue south to the extension of Plainfield Road. Project B4B5 includes improved signaling through the project area, upgrading a side track to a main track, and adding crossovers and connections to reduce delays. The goal of the proposed improvements is to improve operating speeds, minimize congestion and reduce delays. The proposed signal and track improvements will occur within railroad right-of-way. The communities alongside and/or crossing this project area include McCook, LaGrange, LaGrange Park, Broadview, Bellwood, and Melrose Park. Westchester is just west of the project and Maywood is east of the project.
Project B4B5 Public Meeting Notice
Project GS25 Public Hearing - February 28, 2008
Public Meeting on Project P1 - January 18, 2008
CREATE project P-1 near 63rd and State Streets, which is proposed to expand the railroad system capacity, improve railroad operations, reduce train delays and congestion, thereby improving air quality, and increase safety. The proposed plan does not require permanent property acquisition or relocation of businesses. Temporary construction access easements may be required during construction. Two viaducts (60th and 66th streets) are recommended for closure. Drainage improvements for the 61st Street viaduct will be included.