Public Information Notice #2
CREATE Program FP&PS Modification
CREATE Project EW2/P2/P3
Date: May 8, 2009
The Federal Highway Administration, Illinois
Department of Transportation, Chicago Department of Transportation
and Association of American Railroads have agreed to modifications
to the linked CREATE Project EW2/P2/P3. In particular, after some
design changes, the EW2 project has been extended south of its
former terminus at 80th St, to approximately the Dan Ryan
Expressway on the East, and 91st St. on the South. The
extension includes additional rail trackwork as well as utilizing an
existing bay on an existing railroad-over-railroad bridge north of
87th St. It also includes a new railroad bridge over 87th
and 88th Sts. The rationale for extending the project is
to further reduce crossover movements that lead to train delays for
freight and Amtrak trains.
Revised Component Project Preliminary Screening
Worksheets for CREATE projects EW2, EW2/P2 and EW2/P2/P3 can be
accessed by clicking
here. These supersede the corresponding sheets
in the CREATE Final Feasibility Plan.
|