Our Projects
Beltway Corridor
B3
Melrose Connection
Location
North Limit | Lake St. |
---|---|
South Limit | Erie St. |
East Limit | 25th Ave. |
West Limit | I-294 |
Daily Trains Affected
27 Freight Trains |
---|
Communities Benefited:
-
Bellwood
Benefits
Prior to the completion of this project, trains departing Proviso Yard on the original single track would block the IHB main lines, preventing other trains from moving through the area at the same time. The second connection on the new rail bridge allows trains to maintain active operation on the IHB at the same time trains are entering and departing Proviso Yard, which greatly increases capacity.



Scope of Work
This project added new track on a new bridge to create a second connection between the Indiana Harbor Belt Railroad (IHB) and Union Pacific’s Proviso Yard.
Project Status
Phase I | Completed |
---|
Phase II | Completed |
---|
Phase III | Completed |
---|