Our Projects
Tower
T3
Roundout
Location
North Limit | Rockland Rd. |
---|---|
South Limit | Elm Rd. |
East Limit | Arcadia Rd. |
West Limit | N Bradley Rd. |
Daily Trains Affected
8 Amtrak | |
---|---|
60 Metra | |
12 Freight |
Communities Benefited:
-
Rondout
Benefits
Reduces the signal systems’ failure rate due to antiquated infrastructure. Increases reliability of train operations at key crossings throughout the region. Reduces Amtrak and Metra delay due to periodic signal failures, which require hand flagging of the interlocking.



Scope of Work
Upgrading of signal systems at major at-grade railroad crossings. May involve communication upgrades to enable remote operation.
Project Status
Phase I | Not Started |
---|
Phase II | Not Started |
---|
Phase III | Not Started |
---|

Project Location Map
Project outlines and locations shown above are approximations and do not necessarily represent final design and construction limits.